Aertec Vacuum Installation
|
Concrete/Block
The 50mm central vacuum pipes will generally go in the ground floor before the concrete floors are finished and upstairs will be piped around the same time as the 1st fix plumbing and electrical is being done. 2nd fixing of wall inlets and the vacuum unit itself can be done towards the end of the build and before final painting. Timber 1st fixing of the 50mm central vacuum pipes will be carried out the same time as the plumbing and electrical 1st fix. 2nd fixing of wall inlets and the vacuum unit itself can be done towards the end of the build and before final painting. Because there are so many different types of house builds, we would recommend that you consult with an Aertec engineer before building commences and also during the construction phases to ensure a trouble free and a quality installation. |
|